Please be informed that datacentre will carry out Uninterruptible Power Supply (UPS) System load migration works in SG1 IBX supporting the critical load in Data Hall.

During the load migration works, one source will be fully shut down whereas the other source will remain supported by UPS. UPS redundancy of Telin Singapore's network equipment in datacentre that is supporting your service will be reduced to N.

There will be no service impact expected on your services.

The UPS load migration will be carried out one at a time.

13th July 2019; 0930 hrs to 1330 hrs (GMT+8)
14th July 2019: 0930 hrs to 1330 hrs (GMT+8)

Expected length: 4hrs per PDU

 

After the work, the related source will be transferred back to UPS via utility.



Wednesday, July 10, 2019



« Back